Biogas plant in Suchohrdly
The new biogas plan was put into operation in Suchohrdly close to Miroslav. The TEDOM s.r.o. was the general supplyer of plant. This project is a agricultural biogas plant for processing slurry and corn silage.The plant construction was started in April 2007, the technology istallation was finished at the beginning of August. The starting up phase of biogas plant was demanding on time process, likely this phase was finished without any problems. At the beginning of November the TEDOM company was able to fulfill all project parameters and the plant is running with nominal output.
Basic parameters of project:
Fermenters: 2 x 1500 m3
Final reservoir: 4300 m3
Batch of substrate: tank 80 m3, sludge dispenser 2 x 16 m3
Cogeneration: TEDOM Cento 2 x 170 SP bio (2 x 165 kWel.)